Address:
Architect/Engineer:
Contractor:
Original Budget Projection:
Design Start Date:
Design End Date:
Construction Start Date:
Construction End Date:
|
6301 Pat Ave.
STOA Architects
Daniels Building & Construction
$5,079,300
July 2008
February 2009
June 2009
December 2009
|
Project Description:
Renovation will include: Americans with Disabilities Act requirements, restroom renovations, upgrades to heating and air systems, plumbing systems, the kitchen and electrical systems. A new security system will be installed. Construction documents are complete and bids are due in early April. |